Embassy of China - Flats
| Executed works: | 32 apartements + underground parking |
| Location: | Sint-Stevens-Woluwe |
| Term: | 18 calendar months |
| Starting date: | 04/2000 |
| Amount (VAT excl.): | 4.214.190 EUR |
| Client: | Chinese Ambasade in België |
| Architect: | Eyers J. (Linden-Lubbeek) |
| Engineering Office(s): | VFD (Mechelen) - Stability HUGO VANDERBEKEN (Kampenhout) - Technical equipment VENAC (Grimbergen) - Acoustics |
| General features: | Complete construction, ready to move into. Structure: supporting walls in high speed building brick + limited concrete structure. The digging up of the subsoil had to be integrated in the project. (The building is raised upon a former dumping ground). |
| Particular features: | Surfaces:
Extra security measures: degas installation - risk of explosion of methane gas in the subsoil to be given off. |