Overpass over railway line - Kiewit
 
 
Activities
Civil Engineering
Bridges
 
Contractors
Franki Construct
Willemen Infra
 
Special features
demolition of half of the bridge while keeping the other half in service, while traffic passes over a temporary bridge
 
Location 
N74, Kiewit, Limburg, Belgium
 
Client
Agentschap Wegen en Verkeer
 
Architects
Arcadis
 
Temporary partnership
Franki Construct, Kumpen
 
Engineering Office
Arcadis
 
Construction period 
1 year 10 months
 
Start work 
02-2016
 
End of work 
12-2017
 

The overpass over the Kiewit-Hasselt railway line consists of two bridge decks; one in each travelling direction.
Two bridge deck joints shall be installed for each bridge deck. The joints are of a new type with lower noise emissions than the type that was installed previously.
Two travel lanes will be installed for each bridge half.
A pedestrian lane and a wide bike lane will be installed in both directions. The bike and pedestrian lanes shall be separated from the track through a low construction. This gives the advantage of flexibility for the future. A separate pedestrian bridge will also be contructed.

Some key figures:

  • Precast concrete girders: 4,100 m; 192 pieces
  • Reinforced concrete: 6,100 m³
  • Reinforcing steel: 750,000 kg
  • Surfacing (Paving): 33,500 m²
  • Sewer system: 500 m
     
Franki Construct

Kartuizersweg 1
2550 Kontich (Belgium)
tel +32 3 821 16 80
FCVINFO@franki.be
www.franki.be

Since 1998 Franki Construct has been part of Willemen Groep, the largest family construction group in Belgium.
Willemen Infra

Booiebos 4
9031 Drongen (Belgium)
tel + 32 9 282 60 30
infra@willemeninfra.be
website

Willemen Infra came into being on 1 July 2018 as a result of the merger between Aswebo, Aannemingen Van Wellen and the infrastructure department of Kumpen and is a leading road builder and asphalt and concrete manufacturer.
     © Willemen Groep