E17 - Deinze-Kruishoutem
 
 
Activities
Road construction
General roadworks
Asphalt works
Concrete works
 
Contractor
Willemen Infra
 
Location 
E17, Deinze, Oost-Vlaanderen, Belgium
 
Client
Agentschap Wegen en Verkeer
 
Price
€13.698.000
 
Construction period 
4 months
 
Start work 
05-2013
 
End of work 
09-2013
 

This class 8 contract comprised the structural maintenance between Kruishoutem and Nazareth. The implementation period was 100 calendar days. During the implementation period, the entire roadway, the hard shoulder and the foundation were dug up. These were replaced by a foundation in roller compacted concrete, an asphalt sandwich layer and a roadway in continuous reinforced concrete. When resurfacing the roadway, certain on and off ramps for the Deinze/Nazareth and Kruishoutem complexes were given a new top layer.

The entire contract was executed in four phases:

In the first phase, the preliminary work was executed, such as installation of hard shoulders, creating crossways, etc. The two following intermediate periods concerned the actual work. During these, traffic on the E17 passed through 2x2 narrowed lanes. The last phase concerned finishing and opening up the roadway.

To limit disruption to traffic in the first two phases and during phase changes, work was done only at night. Work was done continuously during the other phases.

View the English version of the movie

Willemen Infra

Booiebos 4
9031 Drongen (Belgium)
tel + 32 9 282 60 30
infra@willemeninfra.be
website

Willemen Infra came into being on 1 July 2018 as a result of the merger between Aswebo, Aannemingen Van Wellen and the infrastructure department of Kumpen and is a leading road builder and asphalt and concrete manufacturer.
     © Willemen Groep