Sectioning post - Asse

Description 

A sectioning post is used to temporarily store the excess electricity in the train network in batteries, and to release it when electricity demand is again higher, for example when a faster train passes.

The building measures 10 m x 20 m, with many cable pits along the outside.

In addition, 600 m² of work on the surrounding grounds was done.

Since 1998 Franki Construct has been part of Willemen Groep, the largest family construction group in Belgium.

 
location 

Project Details

Contractor
Special features 
All rebar is interconnected in order to form an electromagnetically neutral grid.
N9K, Asse, Vlaams Brabant, Belgium
Client 
Eurostation
End User 
Infrabel
Architects 
Eurostation
Engineering Office 
Eurostation
Surface area above ground 
200m²
Surface area subterranean 
200m²
Construction period
6 months
Start work
08-2013
End of work
02-2014