Train wash – Brussels-North

Description 

As a replacement for the present train wash in Schaarbeek, the client NMBS Technics foresaw the construction of a new installation located nearby. The design and study were made by Tuc Rail. The work comprises the installation of bedding, sewerage and road works, an 80 m long concrete train wash and a utility building. The wash system and technical equipment in the building specific to a train wash are not included in this contract and were handled by another contractor. 

  • Building: 185 m²
  • Train wash: 600 m²
  • Bedding: 1 km
  • Roads: 800 m²

Since 1998 Franki Construct has been part of Willemen Groep, the largest family construction group in Belgium.

 
location 

Project Details

Contractor
Leeuwoprit, Evere, Brussels, Belgium
Client 
NMBS
Architects 
TUC Rail
Engineering Office 
TUC Rail
Construction period
7 months
Start work
08-2013
End of work
03-2014