Description
The overpass over the Kiewit-Hasselt railway line consists of two bridge decks; one in each travelling direction.
Two bridge deck joints shall be installed for each bridge deck. The joints are of a new type with lower noise emissions than the type that was installed previously.
Two travel lanes will be installed for each bridge half.
A pedestrian lane and a wide bike lane will be installed in both directions. The bike and pedestrian lanes shall be separated from the track through a low construction. This gives the advantage of flexibility for the future. A separate pedestrian bridge will also be contructed.
Some key figures:
- Precast concrete girders: 4,100 m; 192 pieces
- Reinforced concrete: 6,100 m³
- Reinforcing steel: 750,000 kg
- Surfacing (Paving): 33,500 m²
- Sewer system: 500 m
Â
Since 1998 Franki Construct has been part of Willemen Groep, the largest family construction group in Belgium.
News
24/10/2017 - 08:00
10/10/2017 - 11:45
24/05/2017 - 09:15
11/02/2017 - 12:15
09/02/2016 - 16:15
location
Project Details
Contractors
N74, Kiewit, Limburg, Belgium
Client
Agentschap Wegen en Verkeer
Architects
Arcadis
Temporary partnership
Franki Construct, Kumpen
Engineering Office
Arcadis
Construction period
1 year 10 months
Start work
02-2016
End of work
12-2017