Overpass over railway line - Kiewit

Description 

The overpass over the Kiewit-Hasselt railway line consists of two bridge decks; one in each travelling direction.
Two bridge deck joints shall be installed for each bridge deck. The joints are of a new type with lower noise emissions than the type that was installed previously.
Two travel lanes will be installed for each bridge half.
A pedestrian lane and a wide bike lane will be installed in both directions. The bike and pedestrian lanes shall be separated from the track through a low construction. This gives the advantage of flexibility for the future. A separate pedestrian bridge will also be contructed.

Some key figures:

  • Precast concrete girders: 4,100 m; 192 pieces
  • Reinforced concrete: 6,100 m³
  • Reinforcing steel: 750,000 kg
  • Surfacing (Paving): 33,500 m²
  • Sewer system: 500 m
     

Willemen Infra came into being on 1 July 2018 as a result of the merger between Aswebo, Aannemingen Van Wellen and the infrastructure department of Kumpen and is a leading road builder and asphalt and concrete manufacturer.

Since 1998 Franki Construct has been part of Willemen Groep, the largest family construction group in Belgium.

 
location 

Project Details

N74, Kiewit, Limburg, Belgium
Client 
Agentschap Wegen en Verkeer
Architects 
Arcadis
Temporary partnership 
Franki Construct, Kumpen
Engineering Office 
Arcadis
Construction period
1 year 10 months
Start work
02-2016
End of work
12-2017