Bredabaan - Merksem

Description 

Bredabaan in Merksem was reconstructed from Minister Delbekelaan to Molenlei in 2013. Bredabaan is now a pedestrian shopping street with 2 vehicle lanes, bicycle paths and footpaths, a new tram infrastructure, parking strips and a new Burgemeester Jozef Nolfplein.
Aannemingen Van Wellen not only took care of the construction of a tramway in reinforced concrete, a vehicle lane in 3-layer asphalt, a bicycle path in red asphalt and a footpath in granite tiles, it also carried out the drainage works. The works involved thrust boring in long sections and trench shoring using secant piles. The construction of a tram track with a pre-assembled rail system was another challenge that we were able to rise to at Aannemingen Van Wellen.
 

Willemen Infra - the largest Belgian road construction company - came into being on 1 July 2018 as a result of the merger between Aswebo, Aannemingen Van Wellen and the infrastructure department of Kumpen.

 
location 

Project Details

Contractor
Executed works 
Reconstruction of Bredabaan and Burgemeester Jozef Nolfplein
Bredabaan, Merksem, Antwerpen, Belgium
Client 
Agentschap Wegen en Verkeer Antwerpen
Price 
€17.000.000
Engineering Office 
Technum
Construction period
2 years 3 months
Start work
05-2013
End of work
08-2015