Description
The project consisted of infrastructure work along the track bed platform where railway lines L124 and L26 intersect. Several bridge decks were renovated and noise barriers installed, including 2,000 m² of green walls. For the Moensberg station at Uccle, new platforms have been built. Simultaneous with these main works diverse road, bedding, demolition, earth- and sewerage works were performed.
Some figures:
- Earthworks: 50,500 m³.
- Steel delivered: 680 tonnes.
- Concrete TPG: 8,800 m³.
location
Project Details
Contractor
Horzelstraat 300, Ukkel, Brussels, Belgium
Client
Infrabel
Engineering Office
TUC Rail
Construction period
3 years 5 months
Start work
01-2011
End of work
06-2014